Delridge Pedestrian Bridge Seismic Retrofit

Updated February 7, 2025

What's Happening Now?

Construction retrofits to help the Delridge Pedestrian Bridge better withstand earthquakes is nearly complete. Crews have been working on finishing touches including re-applying sealant that will increase safety and reduce future maintenance, as well as repairing sections of the railing at both ends of the bridge.

The photo below shows two frames. The top photo shows construction crews re-applying sealant to the Delridge Pedestrian Bridge’s deck. The bottom photo shows the completed deck with the new sealant applied.

The photo shows 2 frames. Top shows workers applying sealant. Bottom shows completed sections with anti-slip surface.

The bridge will be closed one more time before construction is complete. We’ll share details about this final closure as they become available.

To receive project updates, sign up to join our project listserv.

Project Overview

Earthquakes could have a major impact on Seattle’s infrastructure. To address seismic risks to city infrastructure, the City of Seattle established a bridge seismic program to assess how vulnerable the City’s bridges were to earthquakes, and to retrofit bridges to better withstand the potential impacts of an earthquake.  

As part of the Levy to Move Seattle, 16 bridges were selected for seismic retrofits, including the Delridge Pedestrian Bridge. The Delridge Pedestrian Bridge is an older bridge built prior to modernizing the seismic design code. The bridge serves as a community asset, particularly for people who live or work at the Cooper School Artist Lofts/Youngstown Cultural Arts Center and want to access the Delridge Playfield, Youngstown Cultural Arts Center, and Southwest Youth and Family Services building.

A pedestrian bridge crossing over Delridge Way SW with a ramp on the left and buildings and trees in the background.

The photo above shows the Delridge Pedestrian Bridge, facing south.

We're not changing the current use and operation of the bridge. The Delridge Pedestrian Bridge seismic retrofits will strengthen existing bridge components and reduce the bridge’s vulnerability to earthquakes. Major construction work includes:  

  • Installing carbon fiber wrapping to strengthen the bridge’s superstructure, columns, and footings. 
  • Separating the bridge’s ramps from its structure and building up a lightweight fill support for the ramps. 
  • Adding new expansion joints at the bridge’s ramps. 
  • Removing, modifying and reinstalling the bridge’s handrails. 
  • Modifying the ends of the bridge’s handrails at new expansion joints. 

Project Area

Overhead view of the Delridge Pedestrian Bridge and surrounding area.

A map showing the location of the Delridge Pedestrian Bridge, Delridge Playfield, and Youngstown Cultural Arts Center. The pedestrian bridge is marked in orange, with nearby bus stops and streets labeled for reference.

What to expect during construction

Construction began in April 2024 and was substantially completed by early January 2025. Crews are now working on finishing touches during temporary bridge closures as we approach the end of construction. 

In addition to temporary bridge closures, we currently anticipate the following construction impacts:   

  • Work in the public right-of-way near your home or business 
  • Temporary on-street parking restrictions, with "no park" signs placed 72 hours in advance
  • Temporary sidewalk and crossing closures for people walking and rolling. Detours will be provided and signed
  • Staged construction equipment and materials as well as noise, dust, and vibrations in the work area
  • Typical weekday work hours of 7 AM – 5 PM, Monday through Friday  

Project Schedule

30% Design Complete
60% Design Complete
90% Design Complete
Final Design  Complete
Construction Begins April 2024

Construction schedules are also subject to change and depend on factors such as weather and availability of crews and materials. 

Funding 

The project is funded through the Levy to Move Seattle. Approved by voters in 2015, the 9-year, $930 million Levy to Move Seattle provides funding to improve safety for all travelers, maintain our streets and bridges, and invest in reliable, affordable travel options for a growing city.  

Get Involved 

We're committed to keeping you informed and working with neighbors to limit construction impacts to the extent feasible. Here are some ways to get more information about the project: 

Materials

Translation and Interpretation 

  • If you need this information translated, please call (206) 775-8734
  • 如果您需要此信息翻譯成中文 請致電 (206) 775-8734
  • Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa (206) 775-8734
  • Si necesita traducir esta información al español, llame al (206) 775-8734
  • Odeeffannoon kun akka siif (206) 775-8734
  • Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi (206) 775-8734
  • የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ፡ (206) 775-8734
  • ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ (206) 775-8734
  • 당신이 번역이 정보를 필요로하는 경우에, (206) 775-8734? 전화 해주십시오. 

Transportation

Adiam Emery, Interim Director
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: (206) 684-7623
684-Road@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Transportation

The Seattle Department of Transportation (SDOT) is on a mission to deliver a transportation system that provides safe and affordable access to places and opportunities for everyone as we work to achieve our vision of Seattle as a thriving, equitable community powered by dependable transportation.