N 41st St Pedestrian Bridge Seismic Retrofit
Updated October 2, 2024
What’s happening now?
UPDATE: We began construction on retrofits to help the N 41st St Pedestrian Bridge Seismic Retrofit better withstand earthquakes on September 30, 2024. We can confirm that the bridge will remain open to people walking for most of the construction. There will likely be a few days when the bridge must be closed, which will be announced in advance. To learn more, please read our messaging in the “What to expect during construction” section below.
N 41st St is closed between Lynden Ave N and Whitman Ave N for the duration of construction (4-6 months). In addition, we are closing car lanes, sidewalks, and crosswalks under the bridge in two phases to divert people walking, rolling, biking, and driving away from where work is occurring. We understand these closures will impact everyone who uses N 41st St and Aurora Ave N regularly and we will do what we can to minimize impacts.
We anticipate that construction will last approximately 4-6 months. Construction schedules are subject to change and depend on factors such as weather and availability of crews and materials To receive project updates, sign up to join our project listserv.
Project Overview
Earthquakes could have a major impact on Seattle’s infrastructure. To address seismic risks to city infrastructure, the City of Seattle established a bridge seismic program to assess how vulnerable the City’s bridges were to earthquakes, and to reinforce bridges to better withstand the potential impacts of an earthquake.
As part of the Levy to Move Seattle, 16 bridges were selected for seismic reinforcements, including the N 41st St Pedestrian Bridge. The N 41st St Pedestrian Bridge is an older bridge constructed in 1936 and provides a more direct connection across Aurora Ave N for the north Fremont neighborhood.
We're not planning on changing the current use and operation of the bridge. The planned seismic retrofits to the N 41st St Pedestrian Bridge include several modifications to strengthen existing bridge components and reduce the bridge’s vulnerability to earthquakes. The following are major construction elements:
- Retrofitting the bridge’s footing.
- Installing carbon fiber wrapping to strengthen the bridge’s towers.
- Repairing cracks and damaged concrete.
- Replacing bolts throughout the bridge.
- Replacement of impacted concrete panels and curb ramps
What to expect during construction
Construction began in September 2024 and is anticipated to last approximately 4-6 months. We will continue to share information on our webpage and through regular email updates. You can sign up online to receive email updates.
N 41st St is closed between Lynden Ave N and Whitman Ave N for the duration of construction. In addition, we are closing car lanes, sidewalks, and crosswalks under the bridge in phases to divert people walking, rolling, biking, and driving away from where work is occurring.
We understand these closures will impact everyone who uses N 41st and Aurora Ave N regularly and we will do what we can to minimize impacts. The phases will include the following closures:
Phase 1
During our first phase of lane closures, the southbound bus lane on Aurora Ave N will be closed between N 40th St and N 42nd St. This phase will include sidewalk and crosswalk closures underneath the bridge, with a sidewalk on one side of the street remaining open at all times. Detours will be provided and signed.
Phase 2
During our second phase of lane closures, the northbound bus lane on Aurora Ave N will be closed between N 40th St and N 42nd St. This phase will include sidewalk and crosswalk closures underneath the bridge, with a sidewalk on one side of the street remaining open at all times. Detours will be provided and signed.
In addition to the bridge, lane, sidewalk, and crosswalk closures, we currently anticipate the following construction impacts:
- Work in the public right-of-way near your home or business
- Temporary on-street parking restrictions, with "no park" signs placed 72 hours in advance
- Staged construction equipment and materials as well as noise, dust, and vibrations in the work area
- Typical weekday work hours of 7 AM – 5 PM, Monday through Friday
Project schedule*
30% Design | Complete |
60 % Dsign | Complete |
90% Design | Complete |
Final Design | Complete |
Construction Begins | September 2024 |
* The schedule is subject to change.
Construction is scheduled to last approximately 4-6 months. Construction schedules are also subject to change and depend on factors such as weather and availability of crews and materials.
Funding
The project is funded through the Levy to Move Seattle. Approved by voters in 2015, the 9-year, $930 million Levy to Move Seattle provides funding to improve safety for all travelers, maintain our streets and bridges, and invest in reliable, affordable travel options for a growing city.
Get involved
We're committed to keeping you informed and working with neighbors to limit construction impacts to the extent feasible. Here are some ways to get more information about the project:
- Sign up for our project listserv to receive weekly project updates
- Email the project team at BridgeSeismicRetrofit@seattle.gov
- Leave a voicemail at (206) 775-8734. A project representative will return your call.
Materials
We’ll update you with project materials such as mailings, flyers, and fact sheets as they are created throughout the construction phase of the project.
Translation and interpretation
If you need this information translated, please call (206) 775-8734.
如果您需要此信息翻譯成中文 請致電 (206) 775-8734.
Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa (206) 775-8734.
Si necesita traducir esta información al español, llame al (206) 775-8734.
Odeeffannoon kun akka siif (206) 775-8734.
Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi (206) 775-8734.
የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ፡ (206) 775-8734.
ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ (206) 775-8734.
당신이 번역이 정보를 필요로하는 경우에, (206) 775-8734? 전화 해주십시오.