Madison - RapidRide G Line: Downtown Seattle to First Hill to Madison Valley
English | Tiếng việt | 中國語文 | 한국어
Moving more people on Madison St with frequent and reliable public transit
Updated: October 27, 2023
What’s happening now?
Sign up for email updates for the latest construction information. Past email updates on posted on the right side of this webpage under "Recent Updates".
Eastbound E Madison St is re-opening between 12th Ave and 16th Ave
We’ve completed most of the paving work in Capitol Hill and E Madison St is re-opening to two-way traffic. We’ll continue working in the roadway to complete the remaining paving, build the new center running bus stations, add red bus lanes, and install other pavement markings. We thank everyone for your continued patience during this closure and ongoing construction.
Partial intersection closure at E Madison St and 19th Ave over 4 weekends
There will be 4 partial street closures at the intersection of E Madison St and 19th Ave while we install electrical conduit and repave the intersection. During this work, access to northbound 19th Ave will be closed at E Madison St. E Madison St will remain open around the work area and 19th Ave north of E Madison St will remain open to local access. Sidewalks will also remain open and the Rt 12 bus will be rerouted around the closure. There will be a signed detour for people driving, directing people to use E Thomas St/E John St and 23rd Ave E.
The closures are scheduled to occur on the following weekends. The work is weather dependent and subject to change:
- October 21 - 22, starting Saturday morning and ending Sunday evening
- October 27 starting at 7 PM through October 30 at 6 AM
- November 3 starting at 7 PM through November 6 at 6 AM
- November 10 starting at 7 PM through November 13 at 6 AM
The map below shows the portion of the intersection that will be closed to traffic.
Changes at the intersection of Madison St and Terry Ave
We replaced the full traffic signal at this intersection with pedestrian signals across Madison St and stop signs on Terry Ave. The new pedestrian signals will allow pedestrians to cross Madison St and access the new center running bus station once it has been built. There are new stop signs on Terry Ave and people driving are now restricted to right turns only from Terry to Madison. We’re installing temporary posts on Madison St at the intersection of Terry to help reinforce the right turn only restrictions. This change also restricts people driving on Madison St from taking left turns onto Terry Ave.
Temporary posts on E Pike St at 11th Ave
We've received several questions about posts that were recently installed in the center turn lane on E Pike St at the 11th Ave intersection. These are temporary posts that were installed to address safety concerns at the intersection while the Route 2 bus is detoured on E Pike St. The detoured westbound Route 2 makes left turns from E Pike St to 11th Ave. Buses need to make the turn from main, outside travel lane. The posts prevent other vehicles from entering the center turn lane, reducing the opportunity for collisions with buses making left turns from the main travel lane. The posts will be removed once the Route 2 is no longer detoured on E Pike St.
King County Metro bus stop closures and relocations
Throughout construction, buses will get rerouted and bus stops will temporarily close or relocate. We're working closely with our partners at King County Metro to reduce impacts to bus riders and prioritize restoring buses to their regular routes and opening bus stops. To receive the most up to date information about bus detours and impacts to bus stops, sign up for King County Metro's Transit Alerts.
You can also use digital mapping tools to plan your bus trip and stay informed about bus detours, bus stop closures, and relocated bus stops. For questions about bus routes or bus stops, you can contact King County Metro customer service at (206) 553-3000.
Sidewalk and crosswalk closures
We are working to maintain pedestrian access by installing protected walkways in the street around construction areas. There is not always enough space to install a protected walkway around construction, and sometimes we need to close a crosswalk or sidewalk. There are signs to indicate where sidewalks or crosswalks are closed. People should follow all signed detours. Longer term sidewalk and crossing closures include:
- Sections of the sidewalk on the south side of E Madison St between Broadway and 12th Ave. Pedestrians are detoured to a protected pedestrian walkway on the north side of the street.
- More information on sidewalk work can be found in our project email updates.
Scheduled night work
- October 27
- Demo at the intersection of E Madison St and 19th Ave on the north side
- November 3
- Demo at the intersection of E Madison St and 19th on the north side and at driveways on the north side east of 19th Ave
- November 10
- Demo at the intersection of E Madison St and 19th on the north side and at driveways on the north side west of 19th Ave
The contractor has obtained the necessary permits to work at night. The noisest work will end by 10 PM.
Construction overview
Construction for the project is about 65% complete and anticipated to be completed in summer 2024. We're working to make progress on construction as safely and efficiently as possible. Typical work hours are between 7 AM - 5 PM. The contractor has obtained a noise variance to complete construction activities within allowable noise limits for work outside these hours.
See the latest updates on construction in the Recent Updates section of this webpage (on the right side). For updates prior to 2023, see our weekly email archive. To stay up to date on construction, sign up for email updates.
Scroll down to:
- Learn about project benefits
- View the final design
- Learn about construction
- See resources available to neighbors
Project Overview
The Seattle Department of Transportation and King County Metro are partnering together to bring RapidRide to Madison St.
The Madison St project area is busy, dense, and still growing. Bus rapid transit (BRT) will provide frequent and reliable bus service. The Seattle Department of Transportation (SDOT) will make street improvements to Madison and Spring streets that will allow King County Metro to operate the service as RapidRide G Line from Downtown to Madison Valley.
Madison BRT - RapidRide G Line planning started in 2012 as part of the Seattle Transit Master Plan. The project went through a rigorous process to develop the design with community input and secure federal funding to cover almost half of the project cost. The project is designed to meet the following goals:
Reliability
- Buses will come every 6 minutes during peak times
- Bus only lanes and bus priority at traffic signals reduce travel time (by 5 minutes from Colman Dock to Madison Valley) and improve reliability
- All-door boarding and doors on both sides, so people can board efficiently from new center-running stations (between 9th Ave and 13th Ave)
- ORCA readers at the stations to pay before boarding
- Real-time bus arrival information at stations
Accesibility
- Station platforms level with bus so no stairs to climb
- New curb bulbs, crosswalks, sidewalks, curb ramps, and bike lanes in sections
Equity
- Serves historically underserved neighborhoods with an affordable and reliable transportation option
Upgrades and vibrancy
- Updated utilities and street paving
- New art and landscaping
Please visit the King County Metro website for more information about RapidRide.
Check out this video for an overview of the project:
RapidRide G Line will serve some of Seattle's densest neighborhoods, and it connects to transit across the region (see map).
Key project features
The map above shows key features of the project (see our design sheets for zoomed-in details).
Features include:
Street and lane layout
- Repaving the street and changing the lane layout, including widening Madison by 1 to 2 feet in a few locations and adding bus lanes
- Installing five traffic signals (8th Ave and Spring St, 10th Ave and Madison St, 18th Ave and Madison St, 19th Ave and Union St, Harrison St and MLK) and upgrading existing signals
Bus infrastructure
- Building new bus platforms along the project area, including 4 center-running stations between 9th and 12th avenues
- Placing new bus shelters and other station amenities
- Installing new poles and relocating some overhead trolley wires to match the new street layout
Utilities
- Upgrading the streetlight network in the First Hill neighborhood
- Installing detention tanks to manage stormwater runoff (Madison St between 12th and 13th avenues, 10th between Madison and Seneca streets, and E Pine St between 15th and 16th avenues)
- Water and sewer main replacement east of Broadway
Walking, biking, and community infrastructure
- Building curb bulbs to shorten pedestrian crossings along side streets (Madison St at the intersections of Minor Ave, 10th Ave, 12th Ave, Union St, Pike St, 15th Ave, 18th Ave, 19th Ave, Denny St, John St, and 27th Ave; Spring St at the intersections of 7th, 8th, and 9th avenues)
- Building new and upgrading many existing curb ramps
- Completing landscaping and tree removal/ replacements throughout; with significant landscaping enhancements on Madison St over I-5
- Creating public art (where Madison St, 14th Ave, and Pike St converge)
- Adding bike connections
Final Design
Click the design sheets below to see what the project will look like on your block!
- 1st Ave to 5th Ave (PDF, 2.8 MB)
- 6th Ave to Terry St (PDF, 8 MB)
- Boren Ave to Broadway (PDF, 6.7 MB)
- Broadway to 13th Ave (PDF, 3.3 MB)
- 13th Ave to 17th Ave (PDF, 2.6 MB)
- 17th Ave to E Denny Way (PDF, 2.3 MB)
- E Denny Way to 24th Ave E (PDF, 2.3 MB)
- 25th Ave E to Martin Luther King Jr Way S (includes bus layover) (PDF, 5.5 MB)
What will it look like?
- Rendering above at Central Library shows a station shelter, real time arrival info, station platform at the same level as the bus, and bus lane.
- Rendering at Madison and Terry shows a center running station, pedestrian refuge (protected space in the middle of the street), center running bus lanes, new curb ramps, landscaping, station shelters, and real time arrival info.
- Rendering at Madison and 12th Ave shows a center running station, new curb ramps, pedestrian refuge (protected space to wait in the middle of the street), bus lanes, landscaping, and new curb ramps.
- Rendering at Madison and E John St shows a station platform level with the bus, bus only lane, new curb ramp, yellow tactile strip for people with vision impairments, station shelter, and real time arrival info.
Left turn restrictions
The new center-running stations and center bus lanes require restricting left turns at several intersections. People driving will need to use alternate routes and make left turns where they are permitted. Click on the links below to see maps showing intersections where left turns will be restricted and alternative routes for drivers.
Please note that the cross-sections are typical for each section and are not representative of the entire corridor length.
Future lane layout on Madison St between 6th and 7th avenues (facing east)
Existing
Future
- Lane layout will include 2 westbound right turn lanes, a westbound general-purpose lane, a westbound bus lane, 1 eastbound general-purpose lane
Future lane layout on Madison St between 7th and 8th avenues (facing east)
Existing
Future
- Lane layout will include 3 westbound general-purpose lanes, a center-running bus lane (westbound and eastbound) and station platform, and 1 eastbound general-purpose lane
Future lane layout on Madison St between Summit and Boylston avenues (facing east)
Existing
Future
- Lane layout will include 1 westbound general-purpose lane, 1 center-running bus lane and station platform, and 1 eastbound general-purpose lane
Future lane layout on Madison St between 16th and 17th avenues (facing east)
Existing
Future
- Lane layout will include a westbound bus/right turn only lane, a westbound general-purpose lane, an eastbound general-purpose lane, and an eastbound bus/right turn only lane
Preparing for Construction
What to expect during construction
We are working with the construction contractor to build the project as efficiently as possible while maintaining access and mobility, but you can expect to experience some disruptions from construction activities throughout the corridor.
Generally, we anticipate major construction work to be on weekdays between 7 AM and 5 PM, but there will be times crews have to work on weekends and at night.
Work zones
To limit the amount of time that a particular location is distrupted by construction, the construction contractor's major construction activities will be contained within work zones of up to 1,500 feet (about 4-5 blocks) - with at least 1,500 feet between each major work zone. The contractor is permitted to work in up to 4 work zones at a time. We'll monitor to ensure the contractor completes work in one zone and opens it up to traffic before moving on to the next. Minor construction activities that temporarily close a lane for short periods of time will be allowed outside the major work zones and water main work may occur outside the work zones. We send weekly email updates on construction activities and what to expect.
Construction will generally include:
- Demolition and removals
- Utility work (including planned water outages)
- Rebuilding and restriping
Dates when work is restricted
- Thanksgiving Day to New Years Day (winter holiday moratorium) - no construction on 1st Ave
- Pride Fest - no construction between Broadway and 15th Ave
- Capitol Hill Block Party - no construction between Broadway and 15th Ave
- Hospital zone - no closures during the first month after construction starts between I-5 and Broadway
Demolition and removals
We will be demolishing and removing parts of the existing roadway and sidewalks on Madison and Spring streets to replace with new asphalt or concrete. See design sheets for more locations.
What to expect:
- Vibrations nearby as the construction team breaks up the concrete or asphalt
- Loud noises
- Truck traffic to help carry out road debris
- Typical work hours from 7 AM to 5 PM
- Weekend work as needed
- Temporary parking restrictions for months at a time (and permanent parking removal)
- Traffic shifts and detours for people walking, biking, and driving
- Temporary driveway, street, and lane closures
- Intersection closures, typically on weekends
- Flaggers to help direct traffic
- Temporary bus detours and bus stop relocations
Utility work
Click here to view a pdf version.
These include:
- Water main pipe replacements on Madison between Broadway and Martin Luther King Jr Way
- Deep sewer main pipe replacement on Madison between 18th and 22nd
- Storm water detention pipes on 10th between Madison and Pike, on Madison between 12th and 13th, and on Pike between 13th and 14th
What to expect:
- Excavation to remove existing utilities and install new utilities underneath the street
- Temporary water mains placed along the sidewalk and/or in the street
- About 4 planned water outages at and near Madison St; neighbors will be notified in advance of planned outages (see our planned water outage FAQ for more info)
- Loud noise, dust, and vibrations
- Truck traffic
- Some nighttime and weekend work to minimize distruption on neighbors; visit our water outage FAQ for more on what to expect
Rebuilding and restriping
We will be demolishing and rebuilding much of the roadway and some sidewalks along the project area. At this time, we will rebuild the road base and then pave over top with asphalt or concrete. In some locations, only the top layer of asphalt will be removed and repaved. A similar type of work is done for rebuilding sidewalks and driveways. After installing the new road, we will return to paint new striping on the road and install protected bike lanes in sections as designed.
This includes:
- Street surface, base repair, and subbase as needed
- Sidewalks, curbs, and curb ramps
- Painting new markings on the street
What to expect:
- Multiple temporary closures of lanes and driveways to demolish, excavate, rebuild, and pave the road
- Traffic shifts and turn restrictions
- Loud noise, dust, and vibrations
- Truck traffic
- Steel plates to access driveways where it is safe and feasible
- Typical work hours from 7 AM to 5 PM
- Temporary parking restrictions for weeks at a time
- Some nighttime and weekend work to minimize traffic impacts
How long will construction last?
Construction is anticipated to start in fall 2021. We expect construction to take about 2.5 years to complete and the RapidRide G Line to open in 2024. The construction team will complete the work in up to 4 segments at a time.
Will construction block driveways?
Yes. Driveway restrictions needed for paving activities are typically short-term. In spring 2021, we met with many property owners and building managers to discuss specifics for each driveway. Feel free to contact us to request a meeting.
Will there be sidewalk closures?
Yes. In most cases, a walkway will be maintained on at least one side of the street. We'll work with the contractor to maintain access to businesses and residences.
How will parking be impacted?
When the team is working in a particular work zone, parking will be restricted 24/7 for the duration of the work. People will need to park on side streets or off-street parking lots. Parking on much of the corridor will be removed permanently (see this map for parking specifics). Load zones will also be affected, and new load zones will be added on side streets before construction starts.
What happens to my bus stop during construction?
Many bus stops will be temporarily relocated or closed during construction. To stay up to date about current bus stop closures and relocations, please sign up for Metro's Rider Alerts. If a stop is relocated or a bus is detoured, signs will also be posted along the corridor.
Staging area at E Arthur Pl and Martin Luther King Jr Way E with Still Essential Workers art
In preparation for construction, the team identified 6 potential locations for the construction contractor to store equipment and materials near the project area called staging areas. These sites were selected to reduce the construction footprint on Madison St and to enable the contractor to build the project more efficiently. All locations are in the City's right-of-way. Changes to local traffic and access will be required with some of the staging areas, and we're workingwith neighbors to make modifications as needed.
Staging details:
- Staging sites will be surrounded by a temporary chain-link fence
- Contractors will not be allowed to park personal vehicles within staging areas
- Timing will depend on the location but staging could begin as soon as construction starts and may remain for the duration of construction
- Business and resident access will be maintained
- The construction contractor may propose different locations that SDOT would need to approve
Potential locations:
1. Corner of east side of 10th Ave and south side of E Seneca St
2. West side of 7th Ave between Spring and Madison streets
3. North side of E Union St and 13th Ave
4. South side of E Pike St between 13th and 14th avenues
5. North side of E Pine St and West side of 18th Ave
6. South side of E Arthur PL and north side of E Harrison St
Support neighbors during construction
We know construction is difficult on neighbors. Our team is working to coordinate with neighbors, the construction team, and across City departments to lessen the burden of construction as much as possible including:
- Relocating load zones before construction starts
- Working closely with SDOT's Hub team to coordinate with other public and private construction in the area
- Creating signage tailored for the area with wayfinding and construction information
- Outreach team:
- Serves as liaison between construction team and neighbors
- Conducts construction surveys with neighbors to have direct points of contact and learn about needs
- Attends construction meetings and coordinates with construction team to accommodate neighbors as much as possible
- Communicates with neighbors through mailings, social media, weekly email updates, flyers, door-to-door, virtual meetings, phone calls, and web
Supporting local businesses
Businesses will remain open and accessible during our scheduled construction work. Please continue to support local businesses in person or virtually via Central Area Collaborative and Intentionalist. The Central Area Collaborative is partnering with Intentionalist to support Black-owned and small businesses in the Central District neighborhood.
The First Hill Improvement Association has a list of businesses open during COVID-19. This list is updated weekly.
COVID-19 business resources
We're formally partnering with the Office of Economic Development to help neighbors get connected to the right resources depending on your situation. Contact OED to determine the right resource to meet your needs: OED@seattle.gov I (206) 684-8090 I www.seattle.gov/office-of-economic-development
- Small Business Stabilization Fund (apply by November 9, 2021)
- Neighborhood Economic Recovery Fund
- Neighborhood Matching Fund
- WA Flex Fund (recovery loan)
- SBA EIDL (US Small Business Administration Economic Injury Disaster Loan)
- Digital Sales Access Program
- Black-Owned Small Business Website Program
- Connect with a free consultant to help you navigate landlord, lease and eviction moratorium issues
- Food Business Orientation and other events through Seattle Public Libraries
- Connect with free small business advisor with the WA Small Business Development Center
- City of Seattle Small Business Handbook (updated November 2020)
- 4Culture's Round-up of other opportunities
- Other Covid and small business recovery resources
Funding
The Federal Transit Administration (FTA) has allocated $59.9 million in funding from the Small Starts Program to the Madison Bus Rapid Transit (BRT) - RapidRide G Line project for construction. This $59.9 million will cover about 45% of the total Madison BRT - RapidRide G Line project cost. The funding allocation builds on years of work with the Federal Transit Administration to meet the rigorous readiness requirements for the Small Starts Grant. The federal funding for this project is leveraged through Move Seattle, Sound Transit ST3, King County, and Washington State funds.
Timeline | Activities/Milestones |
---|---|
Jan 2013 - May 2014 | Project scope defined |
Jun 2014 - Apr 2015 | Developed and analyzed concept design alternatives, began community engagement |
May 2015 - Oct 2015 | Refined concept design with community engagement |
Nov 2015 | Finalized and shared draft concept design |
Feb 2016 | City Council approved concept design to move forward (also called Locally Preferred Alternative) |
Feb - May 2016 | Validated cost assumptions from concept design before beginning early design |
Spr/Sum 2016 | Community engagement on early design, including individual meetings, community briefings, and a series of open houses in August |
Jan - Feb 2017 | Met with property and business owners to discuss construction options and parking and loading needs |
March 2017 | 2 public meetings (March 9 and 15) and an online open house to share latest project design and get public feedback |
Spr/Sum/Fall 2017 | Continue design process; continue working with property owners, businesses, and residents to complete construction phasing plan; environmental review |
Feb - Mar 2018 | SEPA Determination of Non-Significance comment period (February 25 through March 1); SEPA Appeal Period (March 1 through March 8) |
Summer 2020 | Received the final Readiness and Risk Report from the Federal Transit Administration |
Fall 2020 | Final design |
Late 2020 | Secure Federal Small Starts Grant and finalize funding agreements with Sound Transit and Seattle City Council |
Fall 2021 | Construction anticipated to start and take about 30-36 months to complete |
2024 | Madison St BRT service begins (as RapidRide G Line) |
February 2022
- Construction notice - E Pine St block closure between 15th and 16th (English)
- Construction notice - E Pine St block closure between 15th and 16th (Russian)
- Construction notice - E Pine St block closure between 15th and 16th (Chinese - Simplified)
- Construction notice - E Pine St block closure between 15th and 16th (Chinese - Traditional)
January 2022
September 2021
- Project overview fact sheet (English)
- Construction fact sheet (English)
- Construction mailer (English, Chinese - Simplified, Korean, Vietnamese)
- Construction yard sign (English, Chinese - Simplified, Korean, Vietnamese)
August 2021
- Final design fact sheet (English)
- Final design fact sheet (Chinese - Simplified)
- Final design fact sheet (Korean)
- Final design fact sheet (Vietnamese)
November 2020
October 2020
- Final project design sheets
- 1st Ave to 5th Ave (PDF, 2.8 MB)
- 6th Ave to Terry St (PDF, 8 MB)
- Boren Ave to Broadway (PDF, 6.7 MB)
- Broadway to 13th Ave (PDF, 3.3 MB)
- 13th Ave to 17th Ave (PDF, 2.6 MB)
- 17th Ave to E Denny Way (PDF, 2.3 MB)
- E Denny Way to 24th Ave E (PDF, 2.3 MB)
- 25th Ave E to Martin Luther King Jr Way S (includes bus layover) (PDF, 5.5 MB)
- Federal Transit Administration Environmental Re-Evaluation Approval Letter
August 2020
June 2020
February 2020
January 2020
November 2019
September 2019
July 2019
- 90% Design Outreach Summary
- Open house boards
- Online open house content
- Fact sheet
- Mailed notification
- Federal Transit Administration Environmental Re-Evaluation Consultation worksheet
- 90% project design (design sheets)
- 1st Ave to 9th Ave (PDF, 8.8 MB)
- Boren Ave to 13th Ave (PDF, 8 MB)
- 14th Ave to E Denny Way (PDF, 8.7 MB)
- E Denny Way to MLK Jr Way (PDF, 8.6 MB)
Maps are large files that may take a while to load
March 2019
October 2018
July 2018
February 2018
NEPA Documented Categorical Exclusion Appendices:
- Appendix A Final 30 PCT Plans
- Appendix B Madison Transportation TM
- Appendix C Madison Noise and Vibration
- Appendix D Madison Air Quality DR
- Appendix E Madison HazMat DR
- Appendix F Cultural Resource Assessment
- Appendix G Madison EJ DR
- Appendix H Madison Land Use TM
- Appendix I Madison Visual Quality TM
- Appendix J Madison Public Svc Utilities TM
- Appendix K Madison Energy TM
- Appendix L Madison Wildlife and Veg TM
- Appendix M Madison No Effect Letter
- Appendix N Madison Cumulative Impact
- Appendix O Madison Parking Study
- Appendix P Madison Traffic Ops Update
- Appendix Q Madison EMF and Noise Tech Memo
- Appendix R Concept Design
- Appendix S Errata
- Federal Transit Administration signature letter
- SEPA DNS mailed notification
January 2018
Fall 2017
Summer 2017
- Updated Design Outreach Summary
- 12th Ave, E Madison St, and E Union St walking tour summary
- 12th Ave, E Madison St, and E Union St walking tour handout
- 24th Ave E, E Madison St, and E John St walking tour summary
- 24th Ave E, E Madison St, and E John St walking tour handout
Spring 2017
March 2017
- Open house boards (7 MB)
- Updated design
- Online open house content (8 MB)
- Spring St restriping handout
February 2017
January 2017
November 2016
August 2016
- Fact Sheet
- Open house boards
- Full route
- Presentation (English)
- Presentation (Chinese/中文(简体))
- Presentation (Spanish/Español)
July 2016
January 22, 2016 City Council Meeting
November 16, 2015 Open House
- LPA overview
- Presentation
- Boards
- Project Update
- Concept design plans
- LPA Summary report
- November Outreach report
October 2015
July 2015
May 2015 Online Survey Results In May, the Madison Street BRT project hosted an online survey to seek input on: BRT design options, routing, terminals, and station location priorities for transit service and capital investment design concepts for a Central Area protected bike laneThe results of the survey can be found here.May 2015 Open House
Design Sheets (*Draft concepts for analysis purposes - NOT final designs*)
- Downtown-Marion
- Downtown-Spring
- I-5 to 15th Ave - Side-running
- I-5 to 15th Ave - Center-running with left-door boarding stations
- I-5 to 15th Ave - Center-running with right-door boarding stations
- 15th Ave to 23rd Ave - Side-running
- 15th Ave to 23rd Ave - Center-running
- MLK Jr Way Extension
Reports
- Purpose and Need
- Existing Conditions - Corridor Overview
- Existing Conditions - Multimodal
- Existing Conditions - Transit
- Existing Conditions - Traffic and Safety
January 2015 Online Survey
November 20, 2014 Open House
September 30, 2014 Open House
- Meeting Summary
- Presentation
- Project Overview and FAQ
- Poster Boards (Part 1)
- Poster Boards (Part 2)
- Meeting Summary
September 2014 - Stakeholder Outreach