Project Complete!
This project was completed in 2023.
Rainier Ave S Landslide Mitigation Project
Updated: October 5, 2023
This project was completed in spring of 2023.
Construction of the additional retaining wall panels on Rainier Ave S near S Norfolk St is complete! Wall Three experienced a slide in 2022 and we added retaining wall panels to the southern end of the wall.
If you have any questions or concerns about the Rainier Ave S Landslide Mitigation Project, please contact us at 206-684-ROAD (7623) or 684-ROAD@seattle.gov.
Overview
We're working to address the long-standing surface slides as well as significant overgrowth obstructing the sidewalk along segments of Rainier Ave S from S Carver St to the south City limits near S Ryan St.
Because of limited funds, the project team prioritized the problem areas. In 2016, we installed a 60’ segment of retaining wall and cleared overgrowth from the existing sidewalk to open it up to people walking.
In 2020, we installed the retaining walls outlined within the project map below.
Project Area
Background
SDOT maintains almost 600 retaining walls, most protecting public streets. The average height is 6 feet, and if all the retaining walls and seawalls were lined up end to end, they would extend for 21 miles.
Timeline
Design: Winter 2016 – Fall 2017
Construction: Installed priority retaining wall and cleared sidewalk in 2016; Retaining walls and new sidewalk installed in 2020; additional wall added to southern end of Location 3 in 2023
Anticipated Construction Impacts
General construction impacts will include noise, dust, vibration, lane restrictions, and potential detours for people walking, biking, and driving.
Funding
The project is funded through the City's Landslide Hazard Mitigation Program and managed by SDOT's Street Use division.
Materials
Construction mailer (December 2019)
Project map (2019)
Project map (work completed in 2016)